2018 Jimmy & Rosalynn Carter Work Project taking place in Mishawaka and South Bend.

Site Update

February 2018

The site of the 2018 Jimmy & Rosalynn Carter Work Project experienced endless amounts of snow and rain this February. Although the weather was a continuous challenge, staff, volunteers and contractors have continued to make progress at the site.

What you will see at the site as of February 2018.

  • Street lights are installed and running
  • A site wide fence has been installed
  • 7 of the two story homes that will be completed during the project week are being framed and weatherized for the elements.
    Each of the 21 homes will be at a different stage of completeness during the build week. Some will be at the very beginning stages of framing while others are scheduled to be finished during the project week.

What you will see at the site as of January 2018.

  • Each of the 21 foundations for every new home has been laid
  • Roads, sidewalks and curbs have been installed
  • 4 homes are under construction
    At the start of the Carter Work Project week, each home will be at various stages of completeness. Some homes will be in the initial stage of building, while others will be completed by volunteers during the week.

 

Make an impact by helping prepare & build these homes.

2018 Jimmy & Rosalynn Carter Work Project taking place in Mishawaka and South Bend.

One of the 7 two-story homes under construction

The site of the 2018 Jimmy & Rosalynn Carter Work Project experienced endless amounts of snow and rain this February. Although the weather was a continuous challenge, staff, volunteers and contractors have continued to make progress at the site.

What you will see at the site as of February 2018.

  • Street lights are installed and running
  • A site wide fence has been installed
  • 7 of the two story homes that will be completed during the project week are being framed and weatherized for the elements
    • Each of the 21 homes will be at a different stage of completeness during the build week. Some will be at the very beginning stages of framing while others are scheduled to be finished during the project week.

What you will see at the site as of January 2018.

  • Each of the 21 foundations for every new home has been laid
  • Roads, sidewalks and curbs have been installed
  • 4 homes are under construction
    • At the start of the Carter Work Project week, each home will be at various stages of completeness. Some homes will be in the initial stage of building, while others will be completed by volunteers during the week.

 

Make an impact by helping prepare & build these homes.